Not Started
132

Move 11 ceiling speakers + Crestron → Broadstreet

5/13 → 5/16JA

Conference room TVs & displays

5/13 → 5/16JA

Zoom / Teams Rooms config & cert

5/15 → 5/18MJ

Digital signage / reception display

5/16 → 5/18JA

VoIP provisioning at 1NYP

5/12 → 5/16MJ

Number porting from 55W carrier

5/12 → 5/22MJ

e911 dispatch verification (NY ECRN)

5/15 → 5/16MJ

Acoustic treatment / room calibration

5/14 → 5/17MJ

Tenant orientation walkthrough

5/12 → 5/13DY

Tenant improvement signoff (1NYP)

5/14 → 5/15DY

55W surrender / make-good plan signed

5/10 → 5/15DY

All-hands FAQ + move guide

5/10 → 5/11KA

T-3 reminder + maps to 1NYP

5/12 → 5/12KA

Move-day signage at both lobbies

5/14 → 5/15KA

Welcome packet at 1NYP desks

5/14 → 5/15KA

Update business cards + signatures

5/12 → 5/20KA

Notify customers / vendors of new address

5/15 → 5/22KA

Update Google Business / Maps / web

5/15 → 5/16KA

Order computers

5/11 → 5/12JA

Asset tagging & inventory

5/13 → 5/18JA

Endpoint mgmt (Intune / Jamf)

5/14 → 5/22JA

License procurement (M365, Adobe, Slack)

5/10 → 5/15JA

Printer / MFP install

5/12 → 5/16JA

Decommission old endpoints (NIST 800-88)

5/18 → 5/26JA

E-waste pickup vendor scheduled

5/22 → 5/27JA

Architect produces filing-ready drawings (Alt-2 set)

5/14 → 5/29

GC bid + selection (lump-sum, occupied-space)

5/18 → 6/5

DOB Alt-2 filing submitted (DOB-NOW)

5/29 → 6/1

ACP-5 / ACP-7 asbestos filing

5/29 → 6/5

MEP filings (PL/SP/EL/MH separate apps)

6/1 → 6/12

DOB plan examination & objections

6/1 → 7/3

GC contract execution + COIs

6/5 → 6/19

Submittals + long-lead orders (doors, glass, MEP)

6/8 → 7/10

Site protection, dust barriers, swing-space prep

7/8 → 7/12

Phase-1 occupant relocation within floor

7/10 → 7/13

Asbestos abatement if encountered (contingency)

7/15 → 7/22

Debris removal & rolling tipping schedule

7/13 → 8/21

Layout & metal-stud framing (new walls)

7/27 → 8/7

Electrical rough-in

8/3 → 8/14

Plumbing rough-in (if pantry/wet-stack changes)

8/3 → 8/14

HVAC ductwork modifications

8/3 → 8/14

Sprinkler heads relocated

8/5 → 8/12

Low-voltage rough (data, AV, security)

8/5 → 8/14

Rough-in inspections (DOB / sprinkler / electric)

8/14 → 8/19

Insulation

8/19 → 8/21

Drywall hung

8/21 → 8/26

Tape, spackle, sand (3 coats)

8/26 → 9/2

Prime + paint

9/2 → 9/9

Door frames + hardware

9/2 → 9/9

Glass partitions / front installs

9/4 → 9/11

Millwork install (pantry, reception, built-ins)

9/4 → 9/14

Flooring (carpet tile / LVT / base)

9/9 → 9/16

ACT ceiling tiles + grid

9/9 → 9/14

Final electrical / data terminations

9/14 → 9/18

Sprinkler hydrostatic test + signoff

9/14 → 9/16

DOB final inspection

9/17 → 9/18

Punch list walk + closeout

9/16 → 9/22

Construction substantial completion

9/22 → 9/22

Letter of completion / sign-offs filed

9/22 → 9/30

Asset inventory final pass

5/15 → 5/18MA

Data destruction certificates

5/18 → 5/22MA

Donate / sell residual furniture

5/18 → 5/26MA

Carpet / paint / make-good repairs

5/20 → 5/26MA

Remove signage

5/22 → 5/23MA

Final cleaning crew

5/26 → 5/27MA

Mail forwarding (USPS+FedEx+UPS)

5/13 → 5/15MA

Utility accounts close (ConEd, ISP)

5/26 → 5/28MA

Photographic walkthrough

5/27 → 5/27MA

Landlord punch list / final walkthrough

5/28 → 5/28MA

Keys returned / badges deactivated

5/28 → 5/28MA

Security deposit return initiated

5/28 → 6/5MA

Final seating chart (115 + holds for 150)

5/11 → 5/13MJ

Monitor mounts install (350 desks)

5/13 → 5/16MJ

Phone booths / focus rooms ready

5/14 → 5/16MJ

Lactation / wellness room equipped

5/14 → 5/16MJ

Reception / lobby setup

5/15 → 5/17MJ

Kitchen / breakroom stocked

5/15 → 5/18MJ

Internal signage & wayfinding

5/16 → 5/18MJ

Create domain architecture

5/10 → 5/12

Design local + cloud domain

5/11 → 5/13

Implement domain architecture

5/13 → 5/17

SSO / MFA configuration

5/13 → 5/16

File share / NAS migration & ACL audit

5/13 → 5/22

Email signatures + GAL update

5/15 → 5/18

Print server / printer queues

5/14 → 5/17

Backup & DR validation

5/16 → 5/22

GPO / config baseline review

5/13 → 5/16

Freight elevator booking — 1NYP

5/10 → 5/11MA

Freight elevator booking — 55W

5/10 → 5/11MA

NYC parking / police permit

5/10 → 5/13MA

Crate rental + delivery to 55W

5/12 → 5/14MA

Move all humans 55W → 1NYP

5/13 → 5/15MA

Move-in window (equipment + seating)

5/15 → 5/18MA

IT smart-hands at both sites

5/15 → 5/18MA

Onsite helpdesk presence (post-move)

5/18 → 5/22MA

Setup cloud gateway

5/14 → 5/18MJ

Build new network core

5/12 → 5/14MJ

LTE WAN setup (UniFi LTE Backup Pro)

5/14 → 5/16MJ

Network infrastructure (VLANs, routing)

5/13 → 5/16MJ

WiFi heatmap survey & U7 Pro XGS placement

5/12 → 5/14MJ

Firewall ruleset & VLAN segmentation

5/11 → 5/14MJ

DNS/DHCP cutover plan

5/13 → 5/15MJ

Network monitoring & alerting

5/14 → 5/18MJ

Cable testing & certification (Fluke)

5/14 → 5/17MJ

Patch panel labeling & port map

5/14 → 5/16MJ

Multi-WAN failover testing

5/15 → 5/16MJ

Lessons-learned retro

5/29 → 6/3

Welcome breakfast 1NYP

5/18 → 5/18KA

Floor tours for all-hands

5/18 → 5/19KA

IT helpdesk visible in-person

5/18 → 5/22KA

Ergonomic check / monitor-arm sweep

5/19 → 5/22KA

Daily retros first week

5/18 → 5/22KA

AD accounts created for 150 new hires

5/22 → 5/29KA

Equipment imaged + staged for 150

5/22 → 5/30KA

Day-1 packets prepared (badges, swag)

5/26 → 5/29KA

New hire orientation rooms booked

5/14 → 5/14KA

Buddy program assignments

5/26 → 5/29KA

6/1 onboarding day execution (150)

6/1 → 6/1KA

GL + cyber insurance updated

5/10 → 5/14MJ

OSHA postings at 1NYP

5/14 → 5/14MJ

Fire warden program + evac route

5/14 → 5/18MJ

Evacuation drill

5/22 → 5/22MJ

ADA compliance check

5/14 → 5/15MJ

First aid / AED placement

5/15 → 5/15MJ

Final budget reconciliation

5/26 → 5/28MJ

Order security equipment

5/10 → 5/11DY

Security cameras install + cable

5/13 → 5/17DY

NVR / video retention configuration

5/15 → 5/17DY

Visitor management (Envoy/Verkada)

5/13 → 5/16DY

Alarm system commissioning

5/15 → 5/17DY

EDR / AV deployment to endpoints

5/13 → 5/22DY

Cyber insurance update for new site

5/10 → 5/14DY
In Progress
35

Room layout wireframes

5/4 → 5/12MJ

Architect proposal evaluation

5/4 → 5/12MJ

Architect contract / SOW signed

5/12 → 5/14MJ

Landlord build approvals (per LOA)

5/10 → 5/14MJ

1NYP building rules + COI compliance

5/10 → 5/13DY

After-hours access / loading-dock

5/11 → 5/12DY

Run 350 desktop cat6 plenum lines

5/4 → 5/14JA

Run TV network and power

5/12 → 5/15JA

UPS sizing & install (MDF/IDF)

5/11 → 5/13JA

Rack PDUs & power distribution

5/12 → 5/14JA

Cable management dressing & labeling

5/14 → 5/17JA

IDF/MDF HVAC, fire suppression, lock check

5/12 → 5/13JA

Get computer quotes

5/2 → 5/11JA

Build standard image (Win/Mac)

5/12 → 5/14JA

Permits issued

7/6 → 7/10MJ

Selective demolition — Phase 1 walls

7/13 → 7/24MJ

Light fixture trim out + commissioning

9/11 → 9/16DY

55W move-of-furniture quotes

5/4 → 5/11MJ

Reconfigure existing furniture on floor

5/12 → 5/15JA

Remove old heavy cabinets

5/8 → 5/14MJ

Moving vendor SOW + COI

5/10 → 5/12DY

Packing kits distributed

5/12 → 5/12MA

Order gateway

5/10 → 5/14MJ

Order new ISP services

4/20 → 4/30DY

Clean out old network closets

5/4 → 5/13MJ

Establish MDF/IDF fiber link

5/8 → 5/13MJ

Rack & stack switches

5/10 → 5/15JA

Multi-ISP WAN setup (diverse last-miles)

5/13 → 5/15DY

Daily standup cadence (M–F)

5/10 → 5/28MJ

Risk register live + contingency budget

5/10 → 5/14KA

Vendor COI collection

5/10 → 5/14MJ

Status reporting to leadership (2x/wk)

5/10 → 5/28KA

Punch list & vendor signoff

5/26 → 5/28MJ

Door access control system install

5/13 → 5/16DY

Badge / access provisioning (115)

5/12 → 5/15DY
Blocked
0
Drop tasks here
Done
12

Site evaluation

4/1 → 4/12MJ

Scope creation

4/8 → 4/18MJ

Multi-vendor quotes for scope

4/15 → 4/28MJ

Redesign desks on floor

4/18 → 4/28MJ

Build out new CADs

4/22 → 5/4MJ

Mood board for site

4/25 → 5/2MJ

1NYP LOA executed

4/10 → 4/22DY

Scope computer form factor / specs

4/22 → 4/30JA

Furniture assembly evaluation

4/25 → 5/4MJ

Order network equipment

4/25 → 5/2MJ

Order network cable

4/25 → 5/2MJ

Project kickoff & charter

4/1 → 4/5KA